Workers with Sterling Commercial Roofing place shingles on top of the roof Monday, July 12, 2021, of Mendota High School. The school is getting some improvements throughout the summer.
Mendota High School is getting spruced up over the summer.
The Board committed to three major construction projects, replacing the asphalt shingles on the roof with metal shingles, repaving the parking lot and building a corridor to connect the vocational and main buildings.
The back parking lot is finished, the roof will be completed in the next week, and the corridor will be completed within the next few weeks, Mendota High School officials said.
Workers with Sterling Commercial Roofing carry shingles on the roof of Mendota High School on Monday, July 12, 2021. Plans are to replace the asphalt shingles on the roof with metal shingles. (Scott Anderson)
Workers with Ringland-Johnson Construction build a canopy awning behind Mendota High School off of the auxiliary gymnasium on Monday, July 12, 2021. A corridor will connect the vocational and main buildings. (Scott Anderson)
Workers with Sterling Commercial Roofing work on replacing the shingles in the front of Mendota High School on Monday, July 12, 2021. (Scott Anderson)